Construction Contract Disputes: Clarifying Retention Money, Delays, and Cost Overruns

,

In construction contracts, disputes often arise concerning payment, delays, and additional costs. The Supreme Court case, The President of the Church of Jesus Christ of Latter Day Saints v. BTL Construction Corporation, clarifies how these issues should be resolved. The Court ruled that retention money is part of the contract price, penalties for delays must be clearly established, and additional costs require written agreements. This decision offers guidance for contractors and project owners navigating complex construction agreements.

Building Blocks or Stumbling Blocks? Decoding a Church Construction Clash

This case revolves around a construction contract between The Church of Jesus Christ of Latter-day Saints (COJCOLDS) and BTL Construction Corporation (BTL) for the construction of a meetinghouse facility. A dispute arose regarding payment for completed work, delays in project completion, and additional costs incurred. The central legal question is how to properly allocate financial responsibilities when a construction project faces delays, changes, and eventual termination.

The initial Construction Contract set the price at P12,680,000.00, with a construction timeline from January 15 to September 15, 2000. Several factors, including adverse weather, power outages, and modifications to the construction blueprints through Change Orders Nos. 1 to 12, led to an extension of the Medina Project’s completion date. On May 18, 2001, BTL communicated to COJCOLDS that financial setbacks from another project (the Pelaez Arcade II Project) had impacted their operations. BTL requested permission to bill COJCOLDS based on 95% and 100% project completion, and to assign payments to suppliers, which COJCOLDS approved. However, on August 13, 2001, BTL halted work on the Medina Project due to a lack of funds and rising material costs. COJCOLDS then terminated the contract on August 17, 2001, and hired Vigor Construction (Vigor) to complete the project.

BTL then filed a claim against COJCOLDS before the Construction Industry Arbitration Commission (CIAC). COJCOLDS countered, seeking damages for delays, reimbursements for supplier payments, cost overruns, and attorney’s fees. The CIAC partially favored both parties, ordering COJCOLDS to pay BTL the unpaid balance and attorney’s fees, while BTL was instructed to pay COJCOLDS liquidated damages and reimbursements. COJCOLDS then appealed to the Court of Appeals (CA). The CA modified the CIAC’s ruling, clarifying the amounts due to each party and adjusting the liquidated damages based on a revised assessment of the project delay. Dissatisfied, both COJCOLDS and BTL appealed to the Supreme Court, leading to the consolidated petitions.

The Supreme Court addressed several key issues in this case, starting with the 10% retention money. COJCOLDS argued that the CA erred in treating the retention money as a separate liability, which would inflate their total financial obligation. The Court agreed, referencing the case of H.L. Carlos Construction, Inc. v. Marina Properties Corp., 466 Phil. 182 (2004), where it was established that retention money is:

…a portion of the contract price automatically deducted from the contractor’s billings, as security for the execution of corrective work – if any – becomes necessary.

The Court clarified that the 10% retention money should not be considered a separate liability but rather a part of the overall contract price that is withheld as security. This amount should be deducted from any outstanding balance owed to BTL, preventing an inflated liability for COJCOLDS.

Next, the Court tackled the costs of the concrete retaining wall. BTL argued this construction was not part of the original contract plans, and they should receive additional payment for it. Article 1724 of the Civil Code governs the recovery of additional costs:

The contractor who undertakes to build a structure or any other work for a stipulated price, in conformity with plans and specifications agreed upon with the land-owner, can neither withdraw from the contract nor demand an increase in the price on account of the higher cost of labor or materials, save when there has been a change in the plans and specifications, provided:
(1) Such change has been authorized by the proprietor in writing; and
(2) The additional price to be paid to the contractor has been determined in writing by both parties.

The Court determined that there was no written authorization or agreement for the additional price of the retaining wall. The construction was already incorporated into the original plans and specifications. As for Change Order Nos. 8 to 12, the Court found that COJCOLDS had already made payments directly to BTL’s suppliers at BTL’s request. Thus, BTL’s claim for additional costs for these changes was also denied.

The Court then addressed BTL’s liability for liquidated damages due to project delays. After evaluating the extensions requested by BTL, the Court determined BTL was granted 190 days of extension, setting the completion deadline to March 24, 2001. Since BTL failed to complete the project by this date, the delay was calculated from March 25, 2001, until the contract termination on August 17, 2001, totaling 146 days. Based on the contract, BTL owed COJCOLDS liquidated damages of P12,680.00 per day of delay, which amounted to P1,851,280.00.

Moreover, the Court agreed with the CA that COJCOLDS incurred a cost overrun of P526,400.00 due to BTL’s delays and subsequent contract termination. As such, BTL was held responsible for reimbursing COJCOLDS for this amount, incurred because of BTL’s failure to complete the project as agreed. Finally, the Court determined that BTL had been overpaid by P300,533.49 for the modifications introduced in Change Order Nos. 1 to 12. Since COJCOLDS had paid BTL’s suppliers directly for these changes, BTL was obligated to return the overpayment to COJCOLDS. This ruling is grounded in Article 2154 of the Civil Code:

If something is received when there is no right to demand it, and it was unduly delivered through mistake, the obligation to return it arises.

Regarding attorney’s fees, the Court upheld the general rule that these are not recoverable as damages, unless there is factual, legal, and equitable justification. Since neither party acted in bad faith, as indicated by the partially meritorious claims on both sides, the Court found it inappropriate to award attorney’s fees. Each party was directed to bear its own arbitration costs and costs of the suit.

FAQs

What was the key issue in this case? The key issue was determining the financial responsibilities of both the contractor (BTL) and the project owner (COJCOLDS) concerning payments, delays, additional costs, and damages in a construction project that was eventually terminated. The Supreme Court clarified the handling of retention money, liquidated damages, and cost overruns.
What is retention money in a construction contract? Retention money is a portion of the contract price that is withheld by the project owner as security for the contractor’s proper performance and to cover any necessary corrective work. The Supreme Court clarified that this money is not a separate liability but part of the overall contract price.
How did the Court determine BTL’s liability for project delays? The Court reviewed the extensions granted to BTL and calculated the delay period from the adjusted completion date until the contract was terminated. BTL was then liable for liquidated damages based on a daily rate specified in the construction contract.
Why was BTL required to reimburse COJCOLDS for cost overruns? BTL was responsible for the cost overruns because their failure to complete the project within the agreed timeframe forced COJCOLDS to hire another contractor to finish the work. This resulted in additional expenses that BTL was obligated to cover.
What requirements are necessary to claim additional costs for work outside the original contract? To claim additional costs, the contractor must have written authorization from the project owner for the changes and a written agreement specifying the additional price for the work. The absence of these written agreements prevents the contractor from claiming additional costs.
Why was BTL ordered to return overpayments to COJCOLDS? BTL was ordered to return overpayments because COJCOLDS had directly paid BTL’s suppliers for certain modifications, and BTL had already charged COJCOLDS for those same modifications. This resulted in BTL receiving more than what was owed.
Was bad faith relevant in the decision to award attorney’s fees? Yes, the absence of bad faith from either party led the Court to not award attorney’s fees. Attorney’s fees are only awarded when there’s a clear justification and indication of bad faith from either party.
What happens if the architect grants an extension, but the client doesn’t agree? Per the construction agreement, the architect’s recommendation regarding extensions is controlling. Therefore, it is critical to consider the architect’s recommendations.

This case provides crucial guidance for interpreting construction contracts and resolving disputes. It emphasizes the importance of clear, written agreements, accurate record-keeping, and adherence to contractual terms. By clarifying the treatment of retention money, liquidated damages, and additional costs, the Supreme Court promotes fairness and predictability in the construction industry.

For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.

Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
Source: The President of the Church of Jesus Christ of Latter Day Saints v. BTL Construction Corporation, G.R. No. 176439 and G.R. No. 176718, January 15, 2014

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *