Breach of Construction Contract: Understanding Liquidated Damages and Payment Obligations in Philippine Law

,

In the Philippines, construction contracts are often complex agreements, and disputes can arise regarding payment obligations, work stoppages, and project completion. This case clarifies that a contractor’s unjustified work stoppage can lead to liability for liquidated damages if the contract stipulates such penalties for delays. Moreover, it underscores the importance of adhering to agreed-upon payment terms, particularly when a third-party construction manager’s approval is required before payment is due, affecting the accrual of interest on unpaid billings.

When Townhouse Dreams Meet Contractual Nightmares: Who Pays When Construction Stalls?

This case, ACS Development & Property Managers, Inc. v. Montaire Realty and Development Corporation, revolves around a construction agreement for the Villa Fresca Townhomes in Tagaytay City. ACS Development (ADPROM), the contractor, and Montaire Realty (MARDC), the developer, entered into a contract where ADPROM would construct townhouse units. A dispute arose over Progress Billing No. 9, leading to a work stoppage by ADPROM and subsequent termination of the agreement by MARDC. The central legal question is whether ADPROM was justified in stopping work due to the billing dispute and whether MARDC was liable for interest on unpaid billings. Furthermore, the court examines the validity of liquidated damages imposed on ADPROM for the project’s delay.

The initial Construction Agreement outlined that ADPROM would be paid periodically based on monthly progress billings, less a 10% retention. Angel Lazaro & Associates (ALA) was appointed as the project’s construction manager, responsible for approving these billings. The contract stipulated that payments were contingent upon ALA’s approval. This condition is crucial because it directly impacts when MARDC’s obligation to pay arises and, consequently, whether any delay in payment can be attributed to them.

ADPROM argued that MARDC’s failure to fully pay Progress Billing No. 9 justified its work stoppage. However, the Court of Appeals (CA) found that MARDC did not incur any delay in payment because ALA had not fully approved the billing. The CA emphasized that the parties had agreed that ALA’s approval was a prerequisite for MARDC’s payment obligation. Moreover, ADPROM’s consolidated billing was higher than ALA’s approved amount. This highlights the importance of adhering to contractual terms and the role of third-party construction managers in overseeing payment approvals.

The Supreme Court upheld the CA’s decision, reiterating that ADPROM could not compel MARDC to satisfy the unpaid billings without ALA’s approval. Citing the Construction Agreement, the Court emphasized the explicit terms:

Article III
SCOPE OF OWNER’S RESPONSIBILITY

3.1 [MARDC] shall make payments directly to [ADPROM] based on the latter”s progress billing as approved by [ALA].

Article IV
CONTRACT PRICE AND TERMS OF PAYMENT

x x x x

4.2 Terms of Payment

4.2.3 [MARDC] shall pay [ADPROM] within seven (7) working days from receipt of the progress billing submitted by [ADPROM], duly approved by [ALA].

4.2.5 All payments/releases shall be effected strictly in accordance with the “Scope of Works, Cost Breakdown and Weight Percentage for Billing” attached as Annexes A and C and the stipulations herein provided and upon presentment by [ADPROM] of a written certification certifying as to the percentage of completion and accompanied by a certificate attesting to the said percentage of completion and recommending approval by [ALA] for the appropriate payment thereof, subject to the warranties and obligations of [ADPROM].

Building on this principle, the Court explained that no default could be attributed to MARDC without ALA’s approval. This ruling underscores the importance of clear contractual language in defining payment obligations and the conditions precedent to those obligations. The Court found that as of May 9, 1997, ALA had only recommended payment of a reduced amount, and thus, ADPROM could not fault MARDC for deferring payment of the full amount demanded.

Furthermore, the CA’s imposition of liquidated damages on ADPROM was another critical aspect of the case. Liquidated damages are predetermined amounts stipulated in a contract that one party must pay to the other in case of a breach. In this instance, the Construction Agreement included a clause stipulating liquidated damages for unexcused delays in project completion. The agreement stated:

Article IX
LIQUIDATED DAMAGES

9.1. [ADPROM] acknowledges that time is of the essence of this Agreement and that any unexcused day of delay as determined in accordance with [S]ection 5.1 hereof as defined in the general conditions of this Agreement will result in injury or damages to [MARDC], in view of which, the parties have hereto agreed that for every calendar day of unexcused delay in the completion of its Work under this Agreement, [ADPROM] shall pay [MARDC] the sum of Thirty[-]Nine Thousand Five Hundred (P39,500.00) per calendar day as liquidated damages. Said amount is equivalent to 1/10 of 1% of the Total Contract Price. Liquidated damages under this provision may be deducted by [MARDC] from the stipulated Contract Price or any balance thereof, or to any progress billings due [ADPROM].

The CA justified the award of liquidated damages by citing ADPROM’s unjustified work stoppage, which resulted in a clear disadvantage to MARDC. The Court reiterated that MARDC was allowed to rely on ALA’s findings regarding the percentage of completion and the appropriate payment. ADPROM’s decision to cease work, even with a pending dispute, was deemed a breach of contract. The Supreme Court cited Philippine Charter Insurance Corporation v. Petroleum Distributors & Services Corporation, emphasizing that contracts constitute the law between the parties, and they are bound by its stipulations as long as they are not contrary to law, morals, good customs, public order, or public policy.

This case illustrates the importance of carefully considering all contractual terms before taking any action that could be construed as a breach. ADPROM’s decision to halt construction based on the billing dispute, without fully adhering to the agreed-upon payment approval process, ultimately led to its liability for liquidated damages. The ruling also reinforces the principle that parties must attempt to settle disputes amicably before resorting to drastic measures like work stoppages. In summary, the Supreme Court’s decision underscores the binding nature of construction contracts and the consequences of failing to comply with their provisions.

In contrast to the CA’s ruling, the Supreme Court clarified the imposable interest on the monetary awards after their finality. To be consistent with prevailing jurisprudence, the Court modified the interest rate, stating that all monetary awards shall bear interest at the rate of only six percent (6%) per annum, computed from the time the awards attain finality until full payment.

The ruling in ACS Development & Property Managers, Inc. v. Montaire Realty and Development Corporation has significant implications for the construction industry in the Philippines. It provides clarity on the enforceability of liquidated damages clauses and highlights the importance of adhering to contractual terms regarding payment obligations and dispute resolution. The case also serves as a reminder for contractors and developers to carefully consider the potential consequences of their actions and to seek amicable solutions to disputes before resorting to work stoppages or contract terminations.

FAQs

What was the key issue in this case? The key issue was whether ACS Development (ADPROM) was justified in stopping work due to a billing dispute and whether Montaire Realty (MARDC) was liable for interest on unpaid billings; the court also examined the validity of liquidated damages imposed on ADPROM for project delays.
What is the significance of ALA’s approval in this case? Angel Lazaro & Associates (ALA) was the project’s construction manager, and the Construction Agreement stipulated that payments were contingent upon ALA’s approval of ADPROM’s progress billings, making ALA’s approval a prerequisite for MARDC’s payment obligation.
What are liquidated damages? Liquidated damages are predetermined amounts stipulated in a contract that one party must pay to the other in case of a breach, serving to compensate for potential losses resulting from the breach.
Why was ADPROM held liable for liquidated damages? ADPROM was held liable because their work stoppage was deemed an unexcused delay in project completion, triggering the liquidated damages clause in the Construction Agreement.
What interest rate applies to the monetary awards? The Supreme Court clarified that all monetary awards shall bear interest at the rate of six percent (6%) per annum, computed from the time the awards attain finality until full payment.
What does this case teach about construction contracts? This case underscores the importance of carefully considering all contractual terms before taking actions that could be construed as a breach, such as halting work or terminating the contract.
What is the role of amicable dispute resolution in construction contracts? The case emphasizes that parties must attempt to settle disputes amicably before resorting to drastic measures, like work stoppages or contract terminations, in compliance with the contract’s dispute resolution provisions.
How does this ruling affect contractors and developers in the Philippines? The ruling provides clarity on the enforceability of liquidated damages clauses and highlights the importance of adhering to contractual terms regarding payment obligations and dispute resolution, providing guidance to contractors and developers.

The decision in ACS Development & Property Managers, Inc. v. Montaire Realty and Development Corporation provides valuable insights into the interpretation and enforcement of construction contracts in the Philippines. It emphasizes the importance of clear contractual language, adherence to agreed-upon terms, and the need for amicable dispute resolution. Parties involved in construction projects should carefully review their contracts and seek legal advice to ensure compliance and mitigate potential risks.

For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.

Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
Source: ACS Development & Property Managers, Inc. vs. Montaire Realty and Development Corporation, G.R. No. 195552, April 18, 2016