Construction Delays and Liquidated Damages: Upholding Contractual Obligations in Project Completion

,

The Supreme Court in Werr Corporation International v. Highlands Prime, Inc. ruled that a contractor, Werr, was liable for liquidated damages due to delays in completing a construction project. Despite industry practices suggesting that liquidated damages should cease upon substantial completion (95% completion), Werr failed to prove they reached this threshold before the contract’s termination. This decision reinforces the principle that contractual agreements prevail unless substantial completion is demonstrably achieved, ensuring project owners are compensated for delays when contractors fail to meet completion targets.

The Horizon-Westridge Project Delay: How Far Should Liquidated Damages Extend?

Highlands Prime, Inc. (HPI) contracted Werr Corporation International to construct residential units in Tagaytay. The contract stipulated a completion deadline and imposed liquidated damages for delays. Werr failed to meet the deadline, leading HPI to terminate the contract. The central legal question was whether liquidated damages should be calculated until the contract’s termination or only up to the point of substantial completion, aligning with construction industry practices.

The dispute was brought before the Construction Industry Arbitration Commission (CIAC), which initially ruled that liquidated damages should only accrue until the projected date of substantial completion. However, the Court of Appeals (CA) modified this decision, stating that delay should be computed until the termination of the contract. Werr, as the contractor, argued that the CA erred by disregarding the industry practice of calculating liquidated damages only until substantial completion, citing Articles 1234, 1235, and 1376 of the Civil Code and specific clauses from the Construction Industry Authority of the Philippines (CIAP) documents. HPI, on the other hand, contended that payments made to suppliers after the termination of the contract should be charged against Werr’s retention money and that Werr should cover additional costs incurred due to the delays.

The Supreme Court, in its analysis, emphasized that it was dealing with a petition for review under Rule 45, which generally limits the review to questions of law. Factual issues, such as the credibility of evidence and the existence of surrounding circumstances, are typically not reviewed unless specific exceptions apply. In the context of arbitral awards by the CIAC, this adherence is even more critical due to the specialized nature of the CIAC’s jurisdiction over construction disputes. The Court reiterated the principle that arbitral awards are binding and final, except on questions of law, to encourage the swift resolution of disputes in the construction industry.

Regarding the payments made to suppliers and contractors after the contract’s termination, the Supreme Court upheld the findings of the CIAC and the CA. The Court found that HPI did not adequately prove that these payments were for obligations incurred prior to the termination. The Court emphasized that factual findings of quasi-judicial bodies like the CIAC, which possess expertise in specific areas, are generally accorded finality if supported by substantial evidence. HPI failed to demonstrate any recognized exceptions, such as fraud or grave abuse of discretion, that would warrant a review and reversal of these factual findings.

Addressing the computation of liquidated damages, the Court acknowledged that the issue of how liquidated damages should be computed based on the agreement and prevailing jurisprudence is a question of law subject to review. Clause 41.5 of the General Building Agreement stipulated that Werr would pay liquidated damages for every day of delay. Werr argued that industry practice, as evidenced in CIAP Document No. 102, provides that liquidated damages should not accrue after the date of substantial completion of the project. The Court disagreed with the CA’s initial rejection of industry practice, clarifying that while the autonomy of contracts is paramount, laws and prevailing customs are deemed incorporated into every contract.

The Civil Code provisions, specifically Article 1234 (substantial performance in good faith) and Article 1376 (considering usage or custom in interpreting contracts), support the consideration of industry practices. The Court referenced previous cases where it applied these provisions in construction agreements, determining that substantial completion, typically equated to 95% project completion, could excuse a contractor from paying liquidated damages. The intention of CIAP Document No. 102 to have suppletory effect on private construction contracts was also noted. This means that it can remedy conflicts or fill omissions within the construction agreement.

Despite recognizing the potential relevance of industry practice, the Supreme Court found that Werr could not benefit from it because Werr failed to prove that it had achieved substantial completion of the project before the contract’s termination. Article 20.11 of CIAP Document No. 102 requires the contractor to complete 95% of the work for substantial completion to be considered. Since Werr’s last admitted accomplishment rate was 93.18%, it did not meet this threshold. Werr also failed to demonstrate that it is the construction industry’s practice to project the date of substantial completion and calculate delays based on past progress billings, which was what the CIAC had done. This assumption, without sufficient evidence, was deemed erroneous.

The Court further explained that the intent behind the rules on substantial completion is to ensure fair allocation of costs, allowing the contractor to receive payment for work completed while protecting the project owner from additional expenses. Projecting substantial completion without actual evidence would unfairly burden the project owner. Therefore, the Supreme Court affirmed the CA’s conclusion that liquidated damages should be computed from October 27, 2006, until the contract’s termination, a period of 33 days.

Finally, concerning arbitration costs, attorney’s fees, and litigation costs, the Supreme Court upheld the CA’s decision to divide arbitration costs between the parties, given that both parties recovered claims and neither acted in bad faith. The denial of attorney’s fees and litigation expenses was also affirmed, as no basis for these awards was established.

FAQs

What was the key issue in this case? The key issue was whether liquidated damages for a delayed construction project should be calculated until the contract’s termination or only up to the point of substantial completion, in line with industry practices. The court had to determine the extent to which a contractor is liable for delays when the project is not fully completed.
What are liquidated damages? Liquidated damages are a pre-agreed sum that a party must pay as compensation for failing to meet contractual obligations, such as completing a project on time. These damages are designed to compensate the project owner for losses incurred due to the delay.
What is substantial completion in construction? Substantial completion typically refers to a stage in a construction project when the work is nearly complete, often defined as 95% completion. At this stage, the remaining work should not prevent the normal use of the completed portion.
What is CIAP Document No. 102? CIAP Document No. 102 is a standard condition of contract for private construction, adopted and promulgated by the Construction Industry Authority of the Philippines. It has a suppletory effect on private construction contracts, meaning it applies when there are conflicts or omissions in the contract.
What did the CIAC initially rule? The CIAC initially ruled that liquidated damages should only accrue until the projected date of substantial completion. They based this on the assumption that the contractor would continue to perform work at the same rate as in previous billings, even after the agreed completion date.
Why did the Supreme Court disagree with the CIAC’s initial ruling? The Supreme Court disagreed with the CIAC because the contractor failed to prove they had achieved substantial completion (95% completion) before the contract was terminated. The Court held that projecting substantial completion without actual evidence unfairly burdens the project owner.
What was the final decision of the Supreme Court? The Supreme Court affirmed the Court of Appeals’ decision, ruling that liquidated damages should be computed from the extended completion date until the termination of the contract. The contractor was liable for damages for the entire period of delay, as they did not reach substantial completion.
What is the significance of this ruling? This ruling reinforces the importance of meeting contractual obligations and provides clarity on how liquidated damages are calculated in construction projects. It underscores that contractors must demonstrate substantial completion to avoid liability for the entire delay period.
Can industry practices override specific contract terms? Industry practices can supplement contract terms if the contract is silent or ambiguous on a particular issue. However, they cannot override express provisions in the contract that clearly address the matter in dispute.

This case highlights the importance of clear, comprehensive contracts in construction projects. It also emphasizes that while industry practices can inform the interpretation of contracts, they do not supersede the need for contractors to fulfill their explicit contractual obligations. The ruling provides a framework for calculating liquidated damages, ensuring project owners are adequately compensated for delays when contractors fail to meet completion targets.

For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.

Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
Source: Werr Corporation International vs. Highlands Prime, Inc., G.R. No. 187543, February 08, 2017

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *