Tag: Breach of Contract

  • Substantial Completion and Contract Termination in Construction Disputes: Philippine Science High School vs. Pirra Construction

    In Philippine construction law, the concepts of substantial completion and valid contract termination are frequently contested. The Supreme Court, in Philippine Science High School-Cagayan Valley Campus v. Pirra Construction Enterprises, clarified the responsibilities and liabilities of parties in construction contracts, especially concerning project completion and contract termination. The Court ruled that Philippine Science High School (PSHS) must compensate Pirra Construction Enterprises (PIRRA) for work completed on two projects because PSHS implicitly accepted one project as substantially complete and unfairly terminated the other. This decision highlights the necessity of clear communication and adherence to contractual agreements in construction projects, impacting how construction companies and government agencies manage their projects.

    When Is a Project ‘Substantially Complete’?: Examining the PSHS-PIRRA Construction Dispute

    This case originated from a dispute between the Philippine Science High School-Cagayan Valley Campus (PSHS) and PIRRA Construction Enterprises (PIRRA) over two construction projects, Project A and Project C. PIRRA filed a complaint with the Construction Industry Arbitration Commission (CIAC) seeking damages against PSHS, alleging that PSHS delayed payment for Project A and wrongfully terminated the contract for Project C. The CIAC initially ruled in favor of PIRRA, a decision which PSHS appealed to the Court of Appeals (CA). The CA partially granted PSHS’s petition but still found them liable for specific payments to PIRRA, leading to the current appeal before the Supreme Court. This case revolves around the interpretation of contractual obligations and the assessment of project completion in the context of construction law.

    The central issue regarding Project A was whether PSHS had treated the project as substantially completed, therefore obligating them to pay PIRRA’s fifth partial billing (PB No. 5). PSHS argued that it never considered Project A substantially complete and that the creation of an Inspectorate Team was merely to assess the work done, not to signify acceptance. However, the Supreme Court sided with the CIAC and the CA, emphasizing that PSHS’s actions indicated an acceptance of substantial completion. The Court noted that PSHS did not object to PIRRA’s request for substantial acceptance and even created the Inspectorate Team to conduct punch listing. Furthermore, PSHS repeatedly referred to PB No. 5 as the final billing for Project A. These actions, combined, suggested that PSHS acknowledged the project was near completion, save for some deficiencies.

    According to Article 1234 of the Civil Code, “If the obligation has been substantially performed in good faith, the obligor may recover as though there had been a strict and complete fulfillment, less damages suffered by the obligee.” This provision is crucial in cases where minor deficiencies remain, but the bulk of the contractual obligations have been met. Here, PIRRA had completed 94.09% of Project A, which the Court deemed a substantial performance that entitled PIRRA to payment for the work done, minus the cost of the remaining defects. The Court reinforced the principle that the COA report, highlighting some defects, did not negate PSHS’s obligation to pay for the already completed portions of the project. The Supreme Court upheld the CA’s computation of the net value of PB No. 5, amounting to P706,077.29, as the appropriate compensation for PIRRA, after accounting for deductions related to defective items and uncompleted work.

    Concerning Project C, the critical question was whether PSHS validly terminated the contract with PIRRA. The CIAC initially found that PSHS breached its obligations by failing to submit revised drawings and issue a variation order (VO) as agreed. In contrast, the CA determined that PSHS validly terminated the contract because PIRRA had suspended work on the project without approval, constituting a default. The Supreme Court sided with the CA on this matter. It highlighted that PIRRA suspended work on Project C as early as October 12, 2009, without PSHS’s approval, even before the November 20, 2009 agreement where PSHS was to provide revised drawings and a VO. While PSHS did not fulfill its obligations under the November 20 agreement, PIRRA was not entirely blameless either; it failed to coordinate with PSHS and did not demand the needed drawings, effectively abandoning the project.

    Under the General Conditions of Contract, PSHS had the right to terminate the contract if PIRRA incurred delays, abandoned the project, or stopped work without authorization. The Court emphasized that PIRRA’s actions justified PSHS’s decision to terminate the contract for Project C. However, the Court also invoked the principle of quantum meruit, which means “as much as one deserves.” This principle ensures that no one unjustly benefits at the expense of another. Even though PIRRA’s contract was validly terminated, it had completed 25.25% of Project C, and it would be unjust for PSHS to retain the benefits of that work without compensation. Therefore, the Supreme Court affirmed the CA’s ruling that PSHS must pay PIRRA the value of the work done on Project C to prevent unjust enrichment.

    In addition to the value of completed work, PIRRA sought compensation for fabricated steel bars, steel awning windows with security grills, and steel railings it had prepared for Project C. The Court determined that PSHS was liable for the value of these fabricated items. Given that the CIAC, with its expertise in construction arbitration, had thoroughly examined the evidence and the CA had affirmed its findings, the Supreme Court saw no reason to disturb their decision. The Court deferred to the CIAC’s technical expertise and the appellate court’s confirmation, reinforcing the principle that specialized tribunals’ findings, when supported by evidence, are generally accorded respect and finality.

    The Supreme Court also addressed the issue of attorney’s fees, affirming the CA’s decision to award them to PIRRA. The Court acknowledged that PIRRA was compelled to litigate to protect its rights and recover what was rightfully due from PSHS. Finally, the Court dismissed PSHS’s claim that as government funds, the amounts due to PIRRA could not be seized under a writ of execution. The Court stated that the government had received and accepted PIRRA’s services and must therefore pay for them. To do otherwise would cause grave injustice to PIRRA and result in unjust enrichment for the government. The Court cited the precedent that justice and equity demand that contractors be duly paid for construction work done on government projects, thereby affirming that PSHS’s funds were not exempt from execution in this context.

    FAQs

    What was the key issue in this case? The key issues were whether Philippine Science High School (PSHS) treated Project A as substantially completed and whether PSHS validly terminated the contract for Project C. The court also considered if PSHS was liable for the value of fabricated materials and attorney’s fees.
    What does substantial completion mean in construction contracts? Substantial completion refers to the point in a construction project where the work is sufficiently complete, allowing the owner to use the facility for its intended purpose, even if minor deficiencies still exist. It triggers the payment of the remaining contract amount, less the cost to correct those deficiencies.
    Under what conditions can a construction contract be terminated? A construction contract can be terminated if one party breaches the agreement, such as through significant delays, abandonment of the project, or failure to comply with contractual obligations. The contract usually specifies the conditions and procedures for termination.
    What is quantum meruit? Quantum meruit is a legal doctrine that allows a party to recover the reasonable value of services or materials provided, even in the absence of a formal contract or when a contract has been terminated. It prevents unjust enrichment by ensuring payment for work performed.
    Why did the court award attorney’s fees to PIRRA Construction? The court awarded attorney’s fees because PIRRA Construction was compelled to litigate to protect its rights and recover what was rightfully due to it under the contracts with the Philippine Science High School (PSHS). This is often granted when one party is forced to sue to enforce their contractual rights.
    Are government funds exempt from execution in construction disputes? No, the Supreme Court held that government funds are not exempt from execution in this case. The court reasoned that the government had received the services of PIRRA Construction and must pay for them to avoid unjust enrichment.
    What was the significance of the COA report in this case? The Commission on Audit (COA) report highlighted some defects in Project A, but the court ruled that it did not negate the Philippine Science High School’s (PSHS) obligation to pay PIRRA Construction for the already completed portions of the project. The COA report was not a valid excuse to delay payment.
    What is a variation order (VO) in construction? A variation order (VO) is a written instruction issued by the project owner or its representative to the contractor, directing a change to the original scope of work. It may involve additions, omissions, or alterations to the design, specifications, or quantities of work.

    The Philippine Science High School-Cagayan Valley Campus v. Pirra Construction Enterprises case serves as a guide for construction companies and government agencies on contract management and dispute resolution. This ruling emphasizes the importance of clear communication, adherence to contractual terms, and fair compensation for completed work. Both parties in construction agreements must act in good faith and fulfill their obligations to avoid costly disputes and legal repercussions.

    For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.

    Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
    Source: PHILIPPINE SCIENCE HIGH SCHOOL-CAGAYAN VALLEY CAMPUS VS. PIRRA CONSTRUCTION ENTERPRISES, G.R. No. 204423, September 14, 2016

  • Rescission Rights: Enforcing Compromise Agreements in Property Sales

    The Supreme Court has affirmed that a party can rescind a compromise agreement without needing a separate court action if the agreement itself allows for rescission upon a breach. This ruling reinforces the binding nature of compromise agreements and clarifies the remedies available when one party fails to meet their obligations. The decision emphasizes that when a compromise agreement, approved by the court, includes provisions for rescission as per an underlying contract (like a Contract to Sell), those terms can be enforced directly through a motion for execution.

    Broken Promises: Can a Bank Rescind a Property Deal After a Failed Settlement?

    This case revolves around a property purchase agreement between Conchita A. Sonley and Anchor Savings Bank (now Equicom Savings Bank). Sonley had agreed to purchase a foreclosed property from the bank, entering into a Contract to Sell. After defaulting on her payments, the bank rescinded the contract. Sonley then filed a complaint, arguing the rescission was invalid because she had substantially paid her obligations. The parties eventually reached a Compromise Agreement, approved by the trial court, where Sonley agreed to repurchase the property.

    However, Sonley again failed to make the agreed-upon payments, leading the bank to file a Manifestation and Motion for Execution, seeking to rescind the Contract to Sell and apply Sonley’s previous payments as rentals. The trial court granted the motion, prompting Sonley to file a Petition for Certiorari, arguing that the court’s judgment did not authorize the issuance of a writ of execution in case of default. The Court of Appeals (CA) denied her petition, holding that the trial court did not abuse its discretion. The Supreme Court was then asked to determine whether the trial court erred in issuing a writ of execution to enforce the rescission of the Compromise Agreement.

    The Supreme Court anchored its decision on **Article 2041 of the Civil Code**, which provides:

    “(i)f one of the parties fails or refuses to abide by the compromise, the other party may either enforce the compromise or regard it as rescinded and insist upon his original demand.”

    This provision, as interpreted in prior jurisprudence, clarifies that no separate action for rescission is necessary. The aggrieved party can simply treat the compromise agreement as rescinded and pursue their original claim.

    The Court emphasized the binding nature of compromise agreements, stating that once approved by the court, they have the force of res judicata. This means the agreement is final and conclusive between the parties, preventing further litigation on the same matter, save for vices of consent or forgery. The Supreme Court referred to the case of Leonor v. Sycip, 111 Phil. 859, 865 (1961) , highlighting that Article 2041 of the Civil Code does not require an action for rescission.

    It is worthy of notice, in this connection, that, unlike Article 2039 of the same Code, which speaks of “a cause of annulment or rescission of the compromise” and provides that “the compromise may be annulled or rescinded” for the therein specified, thus suggesting an action for annulment or rescission, said Article 2041 confers upon the party concerned, not a “cause” for rescission, or the right to “demand” the rescission of a compromise, but the authority, not only to “regard it as rescinded”, but, also, to “insist upon his original demand”. The language of this Article 2041, particularly when contrasted with that of Article 2039, denotes that no action for rescission is required in said Article 2041, and that the party Aggrieved by the breach of a compromise agreement may, if he chooses, bring the suit contemplated or involved in his original demand, as if there had never been any compromise agreement, without bringing an action for rescission thereof. He need not seek a judicial declaration of rescission, for he may “regard” the compromise agreement already “rescinded”.

    In Sonley’s case, the Compromise Agreement explicitly stated that the bank retained the right to rescind the agreement as per the original Contract to Sell. The Contract to Sell, in turn, allowed for rescission if Sonley failed to pay her monthly installments. The Supreme Court found that Sonley’s default triggered this right, and the bank’s motion for execution, which included a prayer for rescission and eviction, served as sufficient notice to Sonley. She even admitted her default in her opposition to the motion.

    The Court also considered the implications of Sonley’s continued occupancy of the property. While she had paid a total of P497,412.76, this amount was deemed a reasonable aggregate rent for her occupation since 2007. Therefore, the Court found no reason to disturb the CA’s decision.

    The Court made clear that the bank had the right to rescind the sale as an option since it was stated in the contract. As it was stated in Clark Development Corporation v. Mondragon Leisure and Resorts Corporation, 546 Phil. 34, 52 (2007):

    “Certainly, a compromise agreement becomes the law between the parties and will not He set aside other than [sic] the grounds mentioned above. In Ramnani v. Cburt of Appeals, we held that the main purpose of a compromise agreement is to put an end to litigation because of the uncertainty that may arise from it. Once the compromise is perfected, the parties are bound to abide by it in good faith. $hould a party fail or refuse to comply with the terms of a compromise of amicable settlement, the other party could either enforce the compromise by a writ of execution or regard it as rescinded and so insist upon his/her original, demand.”

    FAQs

    What was the key issue in this case? The central issue was whether the trial court erred in issuing a writ of execution to enforce the rescission of a Compromise Agreement, when the agreement itself allowed for rescission upon default.
    What is a compromise agreement? A compromise agreement is a contract where parties make mutual concessions to avoid or end litigation. Once approved by a court, it becomes a judgment that is binding and enforceable.
    Does Article 2041 of the Civil Code require a separate action for rescission? No. Article 2041 allows the aggrieved party to treat the compromise agreement as rescinded and pursue their original claim without needing a separate court action for rescission.
    What does res judicata mean in the context of compromise agreements? Res judicata means that once a compromise agreement is approved by the court, it becomes final and conclusive between the parties, preventing further litigation on the same matter, except in cases of fraud or mistake.
    What was the basis for the bank’s right to rescind the agreement in this case? The bank’s right to rescind was based on a clause in the Compromise Agreement that incorporated the rescission terms of the original Contract to Sell, which allowed for rescission if Sonley defaulted on payments.
    Was Sonley entitled to a separate notice of rescission? The Court found that the bank’s motion for execution, which included a prayer for rescission and eviction, served as sufficient notice to Sonley, especially since she admitted her default in her opposition to the motion.
    What happened to the payments Sonley had already made? The court determined that the payments Sonley made were a reasonable aggregate rent for her occupation of the property since 2007.
    What is the practical implication of this ruling for property buyers? Property buyers should be aware that if they enter into a Compromise Agreement and subsequently default, the seller may be able to rescind the agreement without a separate court action, as long as the agreement allows for it.

    In conclusion, the Supreme Court’s decision in Sonley v. Anchor Savings Bank reinforces the enforceability of compromise agreements and clarifies the remedies available when one party breaches the agreement. It underscores that a party can rescind a compromise agreement without needing a separate court action if the agreement itself allows for rescission upon a breach. This ruling has significant implications for property sales and other contractual arrangements where compromise agreements are used to resolve disputes.

    For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.

    Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
    Source: CONCHITA A. SONLEY VS. ANCHOR SAVINGS BANK/ EQUICOM SAVINGS BANK, G.R. No. 205623, August 10, 2016

  • Power Play: Upholding Contractual Obligations in Energy Agreements

    The Supreme Court has affirmed that the National Power Corporation (NPC) must honor its contractual obligations to Southern Philippines Power Corporation (SPPC) regarding a power supply agreement. This decision reinforces the principle that contracts are binding and must be enforced as written, absent any conflict with law or public policy. The Court rejected NPC’s attempt to avoid payment for the full contracted capacity, thereby upholding the stability and predictability of energy agreements.

    Beyond the Blueprint: When Power Plants Evolve, Must Contracts Adapt?

    This case revolves around an Energy Conversion Agreement between NPC and SPPC for a 50-megawatt power plant in General Santos City. SPPC later added a sixth engine, increasing the plant’s capacity to 55 megawatts. NPC refused to pay for the additional capacity, arguing that the agreement only covered the original five engines. The central legal question is whether SPPC’s addition of the engine constituted a breach of contract, thereby excusing NPC from paying for the increased capacity.

    The dispute initially went to the Energy Regulatory Commission (ERC), which ruled in favor of SPPC, ordering NPC to pay for the full 55-megawatt capacity. The Court of Appeals affirmed the ERC’s decision. NPC then appealed to the Supreme Court, raising both procedural and substantive issues. Procedurally, NPC argued that the ERC should have considered its Motion for Reconsideration, even though it was filed late due to reliance on a private courier. Substantively, NPC contended that it was not obligated to pay for the additional capacity because it stemmed from an engine not originally contemplated in the agreement.

    The Supreme Court addressed the procedural issue first. While acknowledging that procedural rules are essential for the orderly administration of justice, the Court also recognized that these rules can be relaxed in certain meritorious cases. Citing Philippine Bank of Communications v. Yeung, the Court reiterated that technical rules should not be strictly applied if they would hinder the achievement of substantial justice. In this case, NPC had a reasonable belief that its chosen method of filing was acceptable, as the ERC had previously allowed similar submissions via private courier. The Court, therefore, found sufficient reason to excuse the delay and address the merits of the case.

    “Aside from matters of life, liberty, honor or property which would warrant the suspension of the Rules of the most mandatory character and an examination and review by the appellate court of the lower court’s findings of fact, the other elements that should be considered are the following: (a) the existence of special or compelling circumstances, (b) the merits of the case, (c) a cause not entirely attributable to the fault or negligence of the party favored by the suspension of the rules, (d) a lack of any showing that the review sought is merely frivolous and dilatory, and (e) the other party will not be unjustly prejudiced thereby.” Sanchez v. Court of Appeals, 452 Phil. 665, 674 (2003) [Per J. Bellosillo, En Banc].

    Building on this principle, the Court underscored that the ERC itself adopts a liberal approach in construing its rules to ensure the expeditious resolution of proceedings on their merits.

    Turning to the substantive issue, the Court examined the Energy Conversion Agreement to determine whether SPPC was contractually prohibited from adding the sixth engine. NPC argued that the agreement specifically mentioned five engines, thus implying a restriction against any additional units. However, the Court found no express prohibition in the agreement. The Court emphasized that the primary objective of the agreement was to ensure a minimum net capacity of 50 megawatts, regardless of the number of engines used to achieve that capacity. According to the project scope and specifications, SPPC was obligated to generate this minimum output. Further, Article 1374 of the Civil Code states: “Various stipulations of a contract must be interpreted or read together to arrive at its true meaning.”

    The Court also noted that the Energy Conversion Agreement was executed under a Build-Operate-Own (BOO) arrangement, granting SPPC considerable autonomy in the operation and management of the power plant. This autonomy included the right to make necessary repairs and improvements to ensure the plant’s operational efficiency. The Agreement allowed SPPC to “do all other things necessary or desirable for the running of the Power Station within the Operating Parameters.” This broad grant of authority supported SPPC’s decision to add an engine to meet its contractual obligations.

    The Court highlighted that the key requirements under the agreement were nomination and demonstration of capacity. First, SPPC had to nominate or guarantee the availability of electricity at the contracted capacity. Second, SPPC had to demonstrate that the power station had the technical capability to produce and deliver the contracted capacity. While SPPC was given an allowance of up to 55 megawatts, the agreement did not specify that this additional capacity had to come exclusively from the original five generating units. This omission, the Court reasoned, was binding on NPC.

    “Contracts cannot be altered for the benefit of one party and to the detriment of another. Neither can this Court, by construction, ‘relieve [a] party from the terms to which [it] voluntarily consented, or impose on [it] those which [it] did not.’” Spouses Cabahug v. National Power Corporation, 702 Phil. 597, 604 (2013) [Per J. Perez, Second Division]

    Ultimately, the Supreme Court upheld the principle that a contract is the law between the parties. Absent any illegality or violation of public policy, the terms of the agreement must be enforced as written. The Court refused to rewrite the contract to favor NPC, emphasizing that parties are bound by the terms to which they voluntarily agreed. Consequently, the Court affirmed the Court of Appeals’ decision, holding NPC liable for the contracted capacity of 55 megawatts from 2005 to 2010.

    FAQs

    What was the key issue in this case? The key issue was whether the National Power Corporation (NPC) was obligated to pay Southern Philippines Power Corporation (SPPC) for additional power capacity generated by a sixth engine added to SPPC’s power plant.
    What did the Energy Conversion Agreement stipulate? The agreement stipulated that SPPC would supply power to NPC, initially from a plant consisting of five engines, with a nominal capacity of 50 megawatts, and allowed for nominations up to 110% of that capacity.
    Why did NPC refuse to pay for the additional capacity? NPC argued that the agreement only covered the original five engines and that the addition of a sixth engine was a unilateral amendment to the contract.
    How did the Supreme Court interpret the Energy Conversion Agreement? The Court interpreted the agreement as not expressly prohibiting the addition of engines, focusing on the requirement that SPPC maintain a minimum net capacity of 50 megawatts, regardless of the number of engines used.
    What is a Build-Operate-Own (BOO) arrangement? A BOO arrangement allows a private entity to finance, construct, own, and operate a facility, such as a power plant, to supply a service (in this case, electricity) to a government entity.
    What was the significance of the nomination and demonstration of capacity? SPPC was required to nominate (guarantee) the availability of electricity and then demonstrate the power station’s technical capability to deliver the contracted capacity to NPC.
    Did the agreement specify where the additional capacity should come from? No, the agreement did not specify that the additional five-megawatt capacity had to be produced only from the original five generating units.
    What principle did the Supreme Court uphold in this decision? The Court upheld the principle that a contract is the law between the parties, and its terms must be enforced as written, absent any illegality or violation of public policy.
    Was NPC’s late filing of its Motion for Reconsideration excused? Yes, the Court excused the late filing due to NPC’s reasonable belief that its method of filing was acceptable, as the ERC had previously allowed similar submissions.

    In conclusion, the Supreme Court’s decision underscores the importance of honoring contractual commitments, particularly in the energy sector, where stability and predictability are crucial. The ruling ensures that agreements are interpreted based on their overall intent and that parties cannot unilaterally avoid their obligations.

    For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.

    Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
    Source: National Power Corporation vs. Southern Philippines Power Corporation, G.R. No. 219627, July 04, 2016

  • Breach of Contract vs. Estafa: When Does a Failed Business Venture Become a Crime?

    The Supreme Court ruled that a failed joint venture, even with misappropriated funds, does not automatically constitute estafa if malicious intent is not proven beyond reasonable doubt. While the Khitris were directed to reimburse the Fukamis for the P400,000.00 investment, the Court acquitted them of estafa, emphasizing that the evidence did not demonstrate malicious intent to defraud, which is a necessary element for the crime. This decision clarifies the distinction between a breach of contractual obligations and criminal fraud, offering guidance on when civil liabilities do not translate to criminal culpability in failed business ventures.

    From Factory Dreams to Apartment Realities: Was It Just a Bad Deal, or a Crime?

    This case revolves around Rosalinda and Fernando Khitri (petitioners) and Hiroshi and Belen Fukami (private complainants). The Fukamis invested P400,000.00 in a joint venture with the Khitris to construct a garments factory. Instead of a two-story factory as allegedly agreed, the Khitris built a two-door studio-type apartment. The Fukamis claimed misappropriation and filed estafa charges against the Khitris, arguing that the funds were misused. The central legal question is whether the Khitris’ actions constituted estafa under Article 315, paragraph 1(b) of the Revised Penal Code (RPC), or merely a breach of contract.

    The Regional Trial Court (RTC) and the Court of Appeals (CA) initially convicted the Khitris of estafa. However, the Supreme Court reversed these decisions, focusing on the element of malicious intent. The Court acknowledged that the first and last elements of estafa were present: the Khitris received money in trust for a specific purpose, and the Fukamis demanded its return. However, the critical elements of misappropriation and prejudice were not sufficiently proven. According to the Court, “[t]he essence of estafa committed with abuse of confidence is the appropriation or conversion of money or property received to the prejudice of the entity to whom a return should be made.”

    The Supreme Court analyzed whether the Khitris acted with malicious intent (dolus malus) in using the funds. The Court emphasized that estafa, as a mala in se offense, requires evil intent to unite with an unlawful act. The Court stated, “[t]he maxim is actus non facit reum, nisi mens sit rea — a crime is not committed if the mind of the person performing the act complained of is innocent.” The Court found that the Khitris did use the money for the intended purpose—construction on the designated lot—albeit with modifications to the original plan. The initial delivery of sewing machines to the constructed apartments by the Fukamis further supported the idea that the structure, though different, was still intended for the garments business.

    Furthermore, the Court noted that the Fukamis voluntarily provided the funds for a joint venture, indicating a business agreement rather than a purely trust-based transaction typically associated with estafa. The alleged damage suffered by the Fukamis, primarily lost profits, was deemed speculative and insufficient to establish prejudice beyond a reasonable doubt. The Court reasoned that where facts are susceptible to multiple interpretations, one consistent with innocence, the accused must be acquitted, upholding the presumption of innocence. Ultimately, the Supreme Court determined that the Khitris’ actions, while perhaps a breach of their agreement, did not rise to the level of criminal fraud.

    The ruling highlights the importance of distinguishing between civil and criminal liabilities in business dealings. A failure to fulfill a contractual obligation does not automatically equate to criminal fraud. In cases of estafa, the prosecution must demonstrate malicious intent, misappropriation, and actual prejudice to the offended party beyond a reasonable doubt. The ruling also underscores the principle that ambiguities in evidence should be resolved in favor of the accused, reinforcing the constitutional right to presumption of innocence. While the Khitris were acquitted of estafa, the Court ordered them to reimburse the Fukamis the P400,000.00, along with interest, to prevent unjust enrichment. This aspect of the ruling ensures that while no crime was committed, fairness and equity are maintained between the parties.

    This decision reinforces the principle that criminal statutes should be strictly construed, and ambiguities should be resolved in favor of the accused. It also clarifies the burden of proof in estafa cases, particularly concerning the element of criminal intent. The case provides a practical guideline for parties involved in business ventures, signaling that disagreements and failures in business arrangements should generally be resolved through civil remedies, unless clear evidence of malicious intent and criminal actions exists.

    FAQs

    What was the key issue in this case? The key issue was whether the actions of Rosalinda and Fernando Khitri in using funds from a joint venture differently than allegedly agreed constituted estafa (swindling) under Article 315 of the Revised Penal Code. Specifically, the court examined whether the element of malicious intent was proven beyond reasonable doubt.
    What is estafa under Philippine law? Estafa is a crime involving fraud or deceit, where one party swindles another out of money or property. It can occur in various forms, including misappropriation of funds received in trust or through abuse of confidence.
    What are the elements of estafa with abuse of confidence? The elements are: (1) receipt of money or property in trust; (2) misappropriation or conversion of such money or property; (3) prejudice to another; and (4) demand for return by the offended party.
    Why were the Khitris acquitted of estafa? The Supreme Court acquitted the Khitris because the prosecution failed to prove the element of malicious intent beyond a reasonable doubt. While the funds were used for a different purpose than allegedly agreed, there was no clear evidence of intent to defraud.
    What is the significance of “actus non facit reum, nisi mens sit rea” in this case? This Latin maxim means “an act does not make a person guilty unless the mind is also guilty.” It underscores the importance of criminal intent in establishing criminal liability; a wrongful act alone is not sufficient for conviction.
    Did the Supreme Court find the Khitris liable for anything? Yes, the Supreme Court directed the Khitris to reimburse the Fukamis the P400,000.00 investment, subject to an annual interest of six percent (6%) from the finality of the decision until full satisfaction, to prevent unjust enrichment.
    What is the difference between criminal and civil liability in this case? Criminal liability involves punishment for a crime, requiring proof beyond a reasonable doubt, while civil liability involves compensation for damages or breach of contract, requiring a lower standard of proof. The Khitris were not found to have committed a crime (estafa) but were still liable to return the money they received.
    What does this case teach about business ventures and legal recourse? The case underscores that not every failed business venture constitutes a crime. Disputes arising from unmet expectations in business agreements are generally civil matters, unless there is clear evidence of criminal intent to defraud.

    This case serves as a reminder that while business agreements may sometimes sour, the threshold for criminal culpability remains high, requiring concrete evidence of malicious intent. It also emphasizes the importance of clear, written agreements to avoid misunderstandings and potential legal disputes. For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.

    Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
    Source: Rosalinda S. Khitri and Fernando S. Khitri vs. People of the Philippines, G.R. No. 210192, July 04, 2016

  • Breach of Contract: Temperate Damages Awarded for Unsubstantiated Actual Losses

    In Republic of the Philippines vs. Alberto Looyuko, the Supreme Court addressed a dispute arising from a refining contract during a sugar crisis. The Court ruled that while both parties experienced losses due to breaches of contract, neither presented sufficient evidence to claim actual damages. Consequently, the Court awarded temperate damages, recognizing the pecuniary losses suffered without precise quantification. This decision highlights the importance of providing concrete evidence when seeking compensation for contractual breaches, especially concerning lost profits and opportunities.

    Sugar-Coated Crisis: Weighing Accountability in Contractual Obligations

    The case originated from a sugar crisis in 1985, which prompted the Philippine government to import raw sugar to stabilize domestic supply. The Department of Agriculture (DA) tasked the National Sugar Refineries Corporation (NASUREFCO) with overseeing the importation. As part of this effort, NASUREFCO contracted with several refineries, including Noah’s Ark Sugar Holdings, owned by Alberto Looyuko, to process and refine the imported raw sugar. The terms of the agreement were formalized in a Refining Contract, outlining the responsibilities of each party.

    Difficulties arose when the delivery of raw sugar to Noah’s Ark encountered delays and discrepancies. Marubeni, the supplier, cited issues with Noah’s Ark’s weighing scale as the reason for suspending deliveries. However, Noah’s Ark contested this claim, alleging that the delay was unjustified and that the delivered sugar was of inferior quality. Consequently, Noah’s Ark retained a portion of the refined sugar, leading the Republic of the Philippines, representing the DA, to file a complaint for the recovery of the retained sugar or its peso value, along with damages.

    The Regional Trial Court (RTC) dismissed the complaint, a decision that was later affirmed by the Court of Appeals (CA). Both courts found that the DA had unduly delayed the delivery of raw sugar and, furthermore, had diverted some of Noah’s Ark’s allocation to other refineries. The courts also noted that the quality of the delivered sugar was below the agreed-upon standard. However, both lower courts awarded damages to each party in the amount of P38,412,000.00. The Supreme Court took on the review, focusing on the evidence supporting the claims for damages and the propriety of offsetting these damages against the value of the retained sugar.

    At the heart of the Supreme Court’s decision lay the evaluation of evidence concerning the damages claimed by both parties. The Court emphasized that actual damages must be proven with a reasonable degree of certainty, supported by competent evidence. Article 2199 of the Civil Code dictates that compensation is awarded only for pecuniary loss that has been duly proven.

    Article 2199 of the Civil Code: “Except as provided by law or by stipulation, one is entitled to an adequate compensation only for such pecuniary loss suffered by him as he has duly proved. Such compensation is referred to as actual or compensatory damages.”

    In this case, the Republic, representing the DA, sought to recover the value of the refined sugar retained by Noah’s Ark, alleging that Noah’s Ark had not delivered the agreed-upon quantity of refined sugar. However, the Republic failed to present concrete evidence of the exact value of the undelivered sugar. Similarly, Noah’s Ark claimed damages for lost income and business opportunities, asserting that the delays and inferior quality of the delivered sugar had harmed its business. Yet, Noah’s Ark did not provide sufficient proof to substantiate these claims.

    The Supreme Court found that neither party had adequately proven their entitlement to actual damages. The Court noted that claims for lost profits and business opportunities require specific evidence, such as financial records or expert testimony, to establish the extent of the loss. Because both parties failed to provide such evidence, the Court concluded that an award of actual damages would be speculative and unwarranted. Therefore, instead of actual damages, the Court awarded temperate damages. Article 2224 of the Civil Code provides the legal basis for temperate damages.

    Article 2224 of the Civil Code: “Temperate or moderate damages, which are more than nominal but less than compensatory damages, may be recovered when the court finds that some pecuniary loss has been suffered but its amount can not be proved with certainty. ”

    The Court determined that both parties had suffered some pecuniary loss as a result of the contractual breaches but that the precise amount of these losses could not be determined with certainty. Therefore, the Court exercised its discretion to award temperate damages, which are intended to provide a fair and reasonable compensation for losses that cannot be precisely quantified. The court cited previous cases, such as Pacific Basin Securities Co., Inc. v. Oriental Petroleum and Minerals Corp., where temperate damages were awarded in situations where pecuniary loss was evident but difficult to prove with certainty.

    Building on this principle, the Supreme Court set the temperate damages for both the Republic and Noah’s Ark at P4,000,000.00 each, considering the estimated losses presented by both parties. The Court also upheld the lower courts’ ruling to offset these damages, meaning that the amounts owed by each party would be balanced against each other. This approach is supported by Article 1283 of the Civil Code.

    Article 1283 of the Civil Code: “If one of the parties to a suit over an obligation has a claim for damages against the other, the former may set it off by proving his right to said damages and the amount thereof.”

    This provision allows for the mutual compensation of debts or damages between parties in a lawsuit, streamlining the resolution of disputes and preventing unnecessary financial transfers. The decision emphasizes the necessity of proving actual damages with concrete evidence, while also acknowledging the role of temperate damages in providing fair compensation when precise quantification is not possible. It underscores the importance of maintaining thorough records and documentation to support claims of financial loss in contractual disputes.

    In conclusion, the Supreme Court’s ruling in Republic of the Philippines vs. Alberto Looyuko serves as a reminder of the evidentiary requirements for claiming damages in breach of contract cases. While the Court recognized the losses suffered by both parties, the failure to provide sufficient proof of actual damages led to the award of temperate damages instead. This decision highlights the importance of diligent record-keeping and the presentation of compelling evidence to substantiate claims for financial loss in legal proceedings.

    FAQs

    What was the key issue in this case? The key issue was whether the damages claimed by both parties in a breach of contract case were adequately proven to justify an award of actual damages.
    What are actual damages? Actual damages are compensation for tangible losses that can be directly linked to a breach of contract or wrongful act and must be proven with a reasonable degree of certainty.
    What are temperate damages? Temperate damages are awarded when some pecuniary loss is proven, but the exact amount cannot be determined with certainty; they are more than nominal but less than compensatory.
    Why were temperate damages awarded instead of actual damages? Temperate damages were awarded because neither party provided sufficient evidence to substantiate their claims for actual damages, such as lost profits or specific financial losses.
    What evidence is needed to prove actual damages in a breach of contract case? To prove actual damages, parties must present concrete evidence, such as financial records, invoices, expert testimony, or other documentation, to establish the extent of the loss directly resulting from the breach.
    What does it mean to “offset” damages? To offset damages means to balance the amounts owed by each party against each other, so that the net amount due is paid by the party with the higher liability.
    What is the significance of Article 1283 of the Civil Code in this case? Article 1283 allows a party to set off their claim for damages against the other party’s claim in the same lawsuit, streamlining the resolution of disputes and preventing unnecessary financial transfers.
    Could Noah’s Ark have improved its case for damages? Yes, Noah’s Ark could have improved its case by presenting financial records, expert testimony, or other documentation to substantiate its claims of lost income and business opportunities resulting from the DA’s breach of contract.
    What was the amount of temperate damages that was awarded? The court awarded each party temperate damages in the amount of P4,000,000.00.

    The ruling in Republic of the Philippines vs. Alberto Looyuko underscores the importance of meticulous record-keeping and the presentation of concrete evidence when claiming damages in breach of contract cases. The awarding of temperate damages serves as a reminder that while courts recognize the potential for financial loss, it is incumbent upon the claimant to provide a clear and convincing basis for their claims.

    For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.

    Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
    Source: REPUBLIC OF THE PHILIPPINES VS. ALBERTO LOOYUKO, G.R. No. 170966, June 22, 2016

  • Breach of Contract and Surety Obligations: Balancing Performance and Liability

    This Supreme Court decision clarifies the responsibilities of contractors and their sureties when construction projects face delays or non-completion. The Court ruled that Vil-Rey Planners and Builders (Vil-Rey) was liable for breach of contract for failing to complete contracted works, while also addressing the extent of Stronghold Insurance Company, Inc.’s (Stronghold) obligations as a surety. This case underscores the importance of fulfilling contractual obligations and the legal consequences of failing to do so in the construction industry, as well as the nuanced role of surety bonds in securing project completion.

    Broken Promises, Bounded Guarantees: Who Pays When Construction Falters?

    This case arose from a series of construction contracts between Vil-Rey and Lexber, Inc. for land filling works. The initial contracts were mutually terminated, leading to a third contract, Work Order No. CAB-96-09, for the remaining work. Under this third contract, Vil-Rey was to receive a downpayment secured by a surety bond from Stronghold, with the balance payable upon completion. The core legal question revolves around whether Vil-Rey breached the third contract and, if so, whether Stronghold, as the surety, is liable for the resulting damages, especially considering an extension granted to Vil-Rey.

    Vil-Rey failed to complete the project by the extended deadline, prompting Lexber to demand payment from Stronghold under the surety bonds. Negotiations failed, leading Lexber to file a complaint against both Vil-Rey and Stronghold. Vil-Rey argued it was owed money for work completed under previous contracts and the third contract. Stronghold contended its liability was limited and extinguished by the contract extension. The Regional Trial Court (RTC) initially ruled in favor of Lexber, holding Vil-Rey and Stronghold jointly and severally liable, a decision later modified upon reconsideration. The Court of Appeals (CA) further modified the RTC’s decision, reducing the liability but affirming Vil-Rey’s breach and Stronghold’s responsibility, leading to the present petitions before the Supreme Court.

    The Supreme Court addressed the issue of whether Vil-Rey breached the contract. The Court emphasized that breach of contract occurs when a party fails to comply with the terms of an agreement without legal justification. Vil-Rey’s managing partner admitted to not completing the works due to a lack of funds, which the Court found to be an admission of failure to fulfill the contractual obligation. The Court highlighted the reciprocal nature of the obligations: Lexber was obligated to pay the balance upon Vil-Rey’s completion of the work, but Vil-Rey’s failure to complete the work triggered its liability for damages.

    The Court referenced Article 2201 of the Civil Code, which distinguishes between damages for obligors acting in good faith versus those acting in bad faith. In this case, absent a showing of bad faith, Vil-Rey was liable for damages that were the natural and probable consequences of the breach. Since Lexber had to hire another contractor to complete the work, the amount paid to the new contractor represented such damages. Therefore, Vil-Rey was liable for this amount, subject to legal interest from the date of delay until full satisfaction.

    However, the Supreme Court also noted that Lexber was in delay regarding its obligation to provide the full downpayment. While the contract stipulated a 50% downpayment against a surety bond, Lexber only paid a partial amount. Thus, Lexber was also liable for damages to Vil-Rey, calculated as interest on the unpaid portion of the downpayment.

    Turning to Stronghold’s liability, the Court addressed the argument that the contract extension extinguished Stronghold’s obligation under the surety bond. Stronghold contended that as a surety, it was discharged from its obligation because the extension was granted without its consent. It relied on the principle that a material alteration of the principal contract, such as an extension of time, releases the surety unless a continuing guarantee exists. The Court rejected this argument, stating that the surety bond guaranteed the full and faithful performance of Vil-Rey’s obligations, and the extension did not make Stronghold’s obligation more onerous.

    The Supreme Court emphasized that the extension aimed to facilitate the completion of the works, which would have ultimately benefited Stronghold by discharging its liability. The Court also noted that Stronghold itself had urged Vil-Rey to complete the project even after the initial deadline. Moreover, Stronghold’s argument about the extension was raised late in the proceedings, which the Court deemed inappropriate. Importantly, the Court reiterated the right of a surety to indemnification from the principal debtor, as stated in Escaño v. Ortigas, Jr.:

    [E]ven as the surety is solidarity bound with the principal debtor to the creditor, the surety who does pay the creditor has the right to recover the full amount paid, and not just any proportional share, from the principal debtor or debtors. Such right to full reimbursement falls within the other rights, actions and benefits which pertain to the surety by reason of the subsidiary obligation assumed by the surety.

    Finally, the Court addressed the issue of attorney’s fees. While the contracts stipulated attorney’s fees equivalent to a percentage of the amount adjudged, the Court reduced the award, citing equitable considerations. The Court considered Vil-Rey’s financial difficulties and Lexber’s partial delay in providing the downpayment. The liquidated damages were reduced to a more reasonable amount to reflect the circumstances.

    FAQs

    What was the key issue in this case? The key issue was determining the liability of a contractor for breach of contract due to project delays and the extent of a surety’s obligation in guaranteeing the contractor’s performance. The Court balanced the responsibilities of both parties involved in the construction project.
    Was Vil-Rey found liable for breach of contract? Yes, the Supreme Court affirmed the Court of Appeals’ decision that Vil-Rey was liable for breach of contract because it failed to complete the construction project as agreed upon in the third contract. The Court found that Vil-Rey’s failure to complete the project on time was a violation of the contractual terms.
    Did the extension of the contract affect Stronghold’s surety obligation? No, the Court ruled that the extension of the contract, granted to Vil-Rey, did not extinguish Stronghold’s obligation as a surety. The Court reasoned that the extension was aimed at completing the works, which would have benefited Stronghold by discharging its liability.
    What damages were awarded to Lexber? Lexber was awarded damages amounting to the cost it incurred to hire another contractor to complete the project, with interest. Additionally, Lexber was awarded attorney’s fees, although the amount was reduced by the Court.
    Was Lexber also found to have any liability? Yes, the Court found that Lexber was also liable for delay in providing the full downpayment as required under the third contract. As a result, Lexber was ordered to pay damages to Vil-Rey, calculated as interest on the unpaid portion of the downpayment.
    What is a surety bond and its purpose? A surety bond is a contract where a surety (like Stronghold) guarantees the performance of an obligation by the principal debtor (Vil-Rey) to the creditor (Lexber). It ensures that if the principal debtor fails to fulfill the obligation, the surety will compensate the creditor for the loss.
    How did the Court determine the amount of attorney’s fees? The Court reduced the attorney’s fees, initially stipulated in the contract, considering the circumstances of the case. The Court took into account Vil-Rey’s financial difficulties and Lexber’s delay in making the full downpayment.
    What is the significance of Article 2201 of the Civil Code in this case? Article 2201 distinguishes between damages for obligors acting in good faith versus those acting in bad faith. It states that an obligor acting in good faith is liable for damages that are the natural and probable consequences of the breach, while an obligor acting in bad faith is liable for all damages reasonably attributed to the non-performance.

    This case provides valuable insights into the dynamics of construction contracts and surety obligations, offering a balanced perspective on the responsibilities and liabilities of both contractors and sureties. The Supreme Court’s decision reinforces the importance of fulfilling contractual obligations and clarifies the circumstances under which sureties can be held liable for the defaults of their principals.

    For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.

    Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
    Source: Vil-Rey Planners and Builders vs. Lexber, Inc., G.R. Nos. 189401 & 189447, June 15, 2016

  • Breach of Contract: No Payment for Unauthorized Dredging Disposal

    The Supreme Court ruled that a contractor who violated the terms of its agreement with the government by improperly disposing of dredged materials is not entitled to payment for that portion of the work. This decision reinforces the principle that contracts have the force of law between parties and must be complied with in good faith. The Court emphasized that unauthorized actions, even if they result in completed work, do not warrant compensation if they breach the contract’s explicit provisions. This case serves as a reminder to contractors to strictly adhere to contractual terms and seek proper authorization for any deviations to ensure they are fairly compensated for their services. The ruling underscores accountability and integrity in government contracts, upholding the importance of following agreed-upon procedures to safeguard public funds and project outcomes.

    Dredging Dilemma: When ‘Side Dumping’ Sinks a Contractor’s Claim

    Movertrade Corporation entered into a contract with the Department of Public Works and Highways (DPWH) for dredging works in Pampanga Bay. The contract specified that dredge spoils were to be disposed of in pre-designated areas. However, Movertrade resorted to “side dumping,” disposing of the dredged materials back into the river. Despite being prohibited from doing so by the DPWH, Movertrade sought payment for this work, arguing that the designated spoil sites were inadequate. The Commission on Audit (COA) denied the claim, leading to a legal battle that ultimately reached the Supreme Court. The central question was whether Movertrade was entitled to payment for work done in violation of the contract’s explicit terms.

    The Supreme Court sided with the COA and DPWH, emphasizing the binding nature of contracts. According to Article 1159 of the Civil Code, obligations arising from contracts have the force of law between the contracting parties and should be complied with in good faith. The Court underscored that Movertrade’s actions directly contravened paragraph 11 of the Contract Agreement, which stipulated the disposal of dredge spoils in pre-designated areas to prevent them from spilling back into the channel.

    Movertrade argued that the DPWH failed to provide adequate spoil sites, justifying their decision to side dump. However, the Court found evidence indicating that the DPWH had indeed provided designated spoil sites, as evidenced by letters from Director Soriquez and Engr. Bustos. The Court also dismissed Movertrade’s argument that Director Soriquez’s earlier letter to the Mt. Pinatubo Commission, mentioning the full capacity of spoil sites, contradicted his later directives. The Court reasoned that it was possible Director Soriquez was unaware of available spoil sites at the time of the earlier letter, and the DPWH may have identified additional sites in the intervening period.

    Furthermore, the Court found Movertrade’s allegations of inadequate, uneconomical, unsafe, and inoperable spoil sites unsupported by evidence. Even if such allegations were true, the Court noted that Movertrade failed to inform the DPWH of these issues or seek a reconsideration of the prohibition on side dumping. Instead, Movertrade continued the prohibited side dumping activities without any explanation or authorization. This defiance of the contract’s terms was a crucial factor in the Court’s decision.

    The Court rejected Movertrade’s attempt to distinguish between “side dumping” and “free dumping,” stating that both methods violated the contract’s requirement to dispose of dredge spoils in designated areas. The fundamental issue was that the dredged materials were dumped back into the river, undermining the very purpose of the dredging project. The Court cited a memorandum from the DPWH, which stated that “[t]he purpose of pre-designated spoil sites is to provide containment of the [dredge] spoils to ensure that the same will not flow back into the channel, otherwise government funds would be wasted because of faulty dredging procedure.”

    Building on this, the Court emphasized that allowing Movertrade to benefit from its breach would be unjust, especially considering that the company had already been paid a significant portion of the contract amount. The Court affirmed the COA’s decision, stating that “[w]e need not belabor that in the absence of grave abuse of discretion, the decisions and resolutions of respondent COA are accorded not only with respect but also with finality, not only on the basis of the doctrine of separation of powers, but also of its presumed expertise in the laws it is entrusted to enforce.” This ruling highlights the judiciary’s deference to the COA’s expertise in auditing government contracts and ensuring accountability in the use of public funds.

    The Supreme Court’s decision underscored the importance of adhering to contractual obligations and seeking proper authorization for any deviations. It also demonstrated that the government will not be compelled to pay for work performed in violation of contract terms, protecting public funds from unauthorized or non-compliant activities.

    FAQs

    What was the key issue in this case? The key issue was whether Movertrade Corporation was entitled to payment for dredging work that was performed using a method (side dumping) that violated the terms of their contract with the DPWH. The contract specified that dredge spoils should be disposed of in pre-designated areas, but Movertrade side dumped them back into the river.
    What is “side dumping” in the context of this case? “Side dumping” refers to the practice of disposing of dredged materials by dumping them back into the river, rather than transporting them to designated spoil sites as stipulated in the contract. This method was prohibited by the DPWH because it undermined the purpose of the dredging project.
    Did the DPWH provide spoil sites as required by the contract? Yes, the Supreme Court found evidence that the DPWH did provide designated spoil sites, including Pascual “A,” Pascual “B,” and the Regala fishpond. Movertrade’s claim that no adequate spoil sites were provided was not supported by the evidence.
    What does the Civil Code say about contractual obligations? Article 1159 of the Civil Code states that obligations arising from contracts have the force of law between the contracting parties and should be complied with in good faith. This means that contracts are legally binding, and parties are expected to fulfill their obligations as agreed.
    Why did the COA deny Movertrade’s claim for payment? The COA denied Movertrade’s claim because the company breached the contract by performing side dumping activities that were not authorized and were in direct violation of the contract’s terms. The COA determined that Movertrade was not entitled to payment for work done in violation of the contract.
    What was Movertrade’s argument for performing side dumping? Movertrade argued that the designated spoil sites were inadequate, uneconomical, unsafe, and inoperable. They also claimed that the term “side dumping” was just used to refer to spoils not being dumped at the spoil sites.
    What is the significance of the Supreme Court’s decision? The Supreme Court’s decision reinforces the principle that contracts are legally binding and must be complied with in good faith. It also affirms the COA’s authority to disallow payments for work performed in violation of contract terms, protecting public funds and ensuring accountability.
    What is grave abuse of discretion in relation to COA decisions? Grave abuse of discretion implies such capricious and whimsical exercise of judgment as is equivalent to lack of jurisdiction. The Supreme Court generally defers to COA’s decisions unless grave abuse of discretion is proven.

    In conclusion, the Supreme Court’s decision in Movertrade Corporation v. COA underscores the critical importance of adhering to contractual obligations, especially when dealing with government contracts. Contractors must ensure they comply with all terms and conditions and obtain proper authorization for any deviations to avoid the risk of non-payment and legal disputes. This case serves as a valuable lesson for all parties involved in government projects, highlighting the need for transparency, accountability, and strict adherence to contractual agreements.

    For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.

    Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
    Source: Movertrade Corporation vs. Commission on Audit and the Department of Public Works and Highways, G.R. No. 204835, September 22, 2015

  • Breach of Construction Contract: Understanding Liquidated Damages and Payment Obligations in Philippine Law

    In the Philippines, construction contracts are often complex agreements, and disputes can arise regarding payment obligations, work stoppages, and project completion. This case clarifies that a contractor’s unjustified work stoppage can lead to liability for liquidated damages if the contract stipulates such penalties for delays. Moreover, it underscores the importance of adhering to agreed-upon payment terms, particularly when a third-party construction manager’s approval is required before payment is due, affecting the accrual of interest on unpaid billings.

    When Townhouse Dreams Meet Contractual Nightmares: Who Pays When Construction Stalls?

    This case, ACS Development & Property Managers, Inc. v. Montaire Realty and Development Corporation, revolves around a construction agreement for the Villa Fresca Townhomes in Tagaytay City. ACS Development (ADPROM), the contractor, and Montaire Realty (MARDC), the developer, entered into a contract where ADPROM would construct townhouse units. A dispute arose over Progress Billing No. 9, leading to a work stoppage by ADPROM and subsequent termination of the agreement by MARDC. The central legal question is whether ADPROM was justified in stopping work due to the billing dispute and whether MARDC was liable for interest on unpaid billings. Furthermore, the court examines the validity of liquidated damages imposed on ADPROM for the project’s delay.

    The initial Construction Agreement outlined that ADPROM would be paid periodically based on monthly progress billings, less a 10% retention. Angel Lazaro & Associates (ALA) was appointed as the project’s construction manager, responsible for approving these billings. The contract stipulated that payments were contingent upon ALA’s approval. This condition is crucial because it directly impacts when MARDC’s obligation to pay arises and, consequently, whether any delay in payment can be attributed to them.

    ADPROM argued that MARDC’s failure to fully pay Progress Billing No. 9 justified its work stoppage. However, the Court of Appeals (CA) found that MARDC did not incur any delay in payment because ALA had not fully approved the billing. The CA emphasized that the parties had agreed that ALA’s approval was a prerequisite for MARDC’s payment obligation. Moreover, ADPROM’s consolidated billing was higher than ALA’s approved amount. This highlights the importance of adhering to contractual terms and the role of third-party construction managers in overseeing payment approvals.

    The Supreme Court upheld the CA’s decision, reiterating that ADPROM could not compel MARDC to satisfy the unpaid billings without ALA’s approval. Citing the Construction Agreement, the Court emphasized the explicit terms:

    Article III
    SCOPE OF OWNER’S RESPONSIBILITY

    3.1 [MARDC] shall make payments directly to [ADPROM] based on the latter”s progress billing as approved by [ALA].

    Article IV
    CONTRACT PRICE AND TERMS OF PAYMENT

    x x x x

    4.2 Terms of Payment

    4.2.3 [MARDC] shall pay [ADPROM] within seven (7) working days from receipt of the progress billing submitted by [ADPROM], duly approved by [ALA].

    4.2.5 All payments/releases shall be effected strictly in accordance with the “Scope of Works, Cost Breakdown and Weight Percentage for Billing” attached as Annexes A and C and the stipulations herein provided and upon presentment by [ADPROM] of a written certification certifying as to the percentage of completion and accompanied by a certificate attesting to the said percentage of completion and recommending approval by [ALA] for the appropriate payment thereof, subject to the warranties and obligations of [ADPROM].

    Building on this principle, the Court explained that no default could be attributed to MARDC without ALA’s approval. This ruling underscores the importance of clear contractual language in defining payment obligations and the conditions precedent to those obligations. The Court found that as of May 9, 1997, ALA had only recommended payment of a reduced amount, and thus, ADPROM could not fault MARDC for deferring payment of the full amount demanded.

    Furthermore, the CA’s imposition of liquidated damages on ADPROM was another critical aspect of the case. Liquidated damages are predetermined amounts stipulated in a contract that one party must pay to the other in case of a breach. In this instance, the Construction Agreement included a clause stipulating liquidated damages for unexcused delays in project completion. The agreement stated:

    Article IX
    LIQUIDATED DAMAGES

    9.1. [ADPROM] acknowledges that time is of the essence of this Agreement and that any unexcused day of delay as determined in accordance with [S]ection 5.1 hereof as defined in the general conditions of this Agreement will result in injury or damages to [MARDC], in view of which, the parties have hereto agreed that for every calendar day of unexcused delay in the completion of its Work under this Agreement, [ADPROM] shall pay [MARDC] the sum of Thirty[-]Nine Thousand Five Hundred (P39,500.00) per calendar day as liquidated damages. Said amount is equivalent to 1/10 of 1% of the Total Contract Price. Liquidated damages under this provision may be deducted by [MARDC] from the stipulated Contract Price or any balance thereof, or to any progress billings due [ADPROM].

    The CA justified the award of liquidated damages by citing ADPROM’s unjustified work stoppage, which resulted in a clear disadvantage to MARDC. The Court reiterated that MARDC was allowed to rely on ALA’s findings regarding the percentage of completion and the appropriate payment. ADPROM’s decision to cease work, even with a pending dispute, was deemed a breach of contract. The Supreme Court cited Philippine Charter Insurance Corporation v. Petroleum Distributors & Services Corporation, emphasizing that contracts constitute the law between the parties, and they are bound by its stipulations as long as they are not contrary to law, morals, good customs, public order, or public policy.

    This case illustrates the importance of carefully considering all contractual terms before taking any action that could be construed as a breach. ADPROM’s decision to halt construction based on the billing dispute, without fully adhering to the agreed-upon payment approval process, ultimately led to its liability for liquidated damages. The ruling also reinforces the principle that parties must attempt to settle disputes amicably before resorting to drastic measures like work stoppages. In summary, the Supreme Court’s decision underscores the binding nature of construction contracts and the consequences of failing to comply with their provisions.

    In contrast to the CA’s ruling, the Supreme Court clarified the imposable interest on the monetary awards after their finality. To be consistent with prevailing jurisprudence, the Court modified the interest rate, stating that all monetary awards shall bear interest at the rate of only six percent (6%) per annum, computed from the time the awards attain finality until full payment.

    The ruling in ACS Development & Property Managers, Inc. v. Montaire Realty and Development Corporation has significant implications for the construction industry in the Philippines. It provides clarity on the enforceability of liquidated damages clauses and highlights the importance of adhering to contractual terms regarding payment obligations and dispute resolution. The case also serves as a reminder for contractors and developers to carefully consider the potential consequences of their actions and to seek amicable solutions to disputes before resorting to work stoppages or contract terminations.

    FAQs

    What was the key issue in this case? The key issue was whether ACS Development (ADPROM) was justified in stopping work due to a billing dispute and whether Montaire Realty (MARDC) was liable for interest on unpaid billings; the court also examined the validity of liquidated damages imposed on ADPROM for project delays.
    What is the significance of ALA’s approval in this case? Angel Lazaro & Associates (ALA) was the project’s construction manager, and the Construction Agreement stipulated that payments were contingent upon ALA’s approval of ADPROM’s progress billings, making ALA’s approval a prerequisite for MARDC’s payment obligation.
    What are liquidated damages? Liquidated damages are predetermined amounts stipulated in a contract that one party must pay to the other in case of a breach, serving to compensate for potential losses resulting from the breach.
    Why was ADPROM held liable for liquidated damages? ADPROM was held liable because their work stoppage was deemed an unexcused delay in project completion, triggering the liquidated damages clause in the Construction Agreement.
    What interest rate applies to the monetary awards? The Supreme Court clarified that all monetary awards shall bear interest at the rate of six percent (6%) per annum, computed from the time the awards attain finality until full payment.
    What does this case teach about construction contracts? This case underscores the importance of carefully considering all contractual terms before taking actions that could be construed as a breach, such as halting work or terminating the contract.
    What is the role of amicable dispute resolution in construction contracts? The case emphasizes that parties must attempt to settle disputes amicably before resorting to drastic measures, like work stoppages or contract terminations, in compliance with the contract’s dispute resolution provisions.
    How does this ruling affect contractors and developers in the Philippines? The ruling provides clarity on the enforceability of liquidated damages clauses and highlights the importance of adhering to contractual terms regarding payment obligations and dispute resolution, providing guidance to contractors and developers.

    The decision in ACS Development & Property Managers, Inc. v. Montaire Realty and Development Corporation provides valuable insights into the interpretation and enforcement of construction contracts in the Philippines. It emphasizes the importance of clear contractual language, adherence to agreed-upon terms, and the need for amicable dispute resolution. Parties involved in construction projects should carefully review their contracts and seek legal advice to ensure compliance and mitigate potential risks.

    For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.

    Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
    Source: ACS Development & Property Managers, Inc. vs. Montaire Realty and Development Corporation, G.R. No. 195552, April 18, 2016

  • Progress Billings and Contractual Obligations: Upholding Contractor’s Valuation in Construction Disputes

    In a construction dispute between Pro Builders, Inc. and TG Universal Business Ventures, Inc., the Supreme Court held that when a project owner fails to act upon progress billings submitted by the contractor within the period specified in their agreement, the owner effectively waives the right to contest the accuracy and veracity of the contractor’s valuation of completed works. This ruling emphasizes the importance of adhering to contractual timelines and fulfilling obligations in construction contracts, ensuring fairness and predictability in payment disputes.

    From Dismal Performance to Disputed Payments: Who Bears the Brunt of Breach in Construction Contracts?

    This case originated from an Owner-Contractor Agreement between TG Universal Business Ventures, Inc. (TG) and Pro Builders, Inc. for the construction of a 15-story building. Dissatisfied with the progress, TG took over the project and subsequently filed a Request for Arbitration with the Construction Industry Arbitration Commission (CIAC) to recover costs to complete the project. Pro Builders, in turn, counterclaimed for unpaid work accomplishment and damages. The CIAC partially ruled in favor of Pro Builders, but this decision was later modified by the Court of Appeals (CA), leading Pro Builders to seek recourse with the Supreme Court.

    The central issue revolved around the valuation of Pro Builders’ accomplished works and whether TG was justified in taking over the project and claiming costs for completing it. Pro Builders argued that the CA erred in relying on an allegedly one-sided joint evaluation of the project and in disregarding the progress billings it had submitted to TG. According to Pro Builders, the progress billings were more accurate and reliable, entitling them to additional payment. TG, on the other hand, contended that Pro Builders had failed to meet project milestones and had incurred delays, justifying the takeover and the claim for costs to complete.

    In analyzing the case, the Supreme Court first addressed the procedural issue of whether the CA had jurisdiction to review the CIAC’s decision. The Court affirmed that under Executive Order (EO) No. 1008 and Rule 43 of the Rules of Court, the CA has the authority to review decisions or awards of quasi-judicial agencies like the CIAC. This procedural aspect confirms the appellate court’s role in ensuring that arbitral decisions are consistent with the law and evidence presented.

    Turning to the substantive issues, the Court delved into the factual question of which party’s valuation of the accomplished works should be credited. The Court emphasized that a question of fact arises when the issue pertains to the truth or falsity of alleged facts. Given that the factual findings of the CA and the CIAC were contradictory, the Supreme Court found it necessary to re-evaluate the evidence presented by both parties.

    The Supreme Court gave credence to Pro Builders’ valuation, pointing out that the alleged joint evaluation conducted by TG was one-sided. The Court cited the expertise of the CIAC in construction arbitration and the fact that TG’s Project Manager had admitted that the assessment of Pro Builders’ accomplishment was done solely by the Project Manager. Moreover, the Court noted that the documents attached to the joint evaluation were self-serving because there was no showing that Pro Builders participated in the computation of their accomplished works. It highlighted the letter from TG’s Project Inspector to Pro Builder’s Project-in-Charge seeking feedback on his evaluation months after the takeover, which undermined the claim that it was a joint effort.

    Building on this principle, the Supreme Court found the progress billings prepared by Pro Builders provided an accurate summary of accomplishments. Citing Article 5.03 of the Agreement, the Court stated that it was the Project Manager’s responsibility to evaluate, certify, and recommend payment of the progress billings within fifteen days. The fact that TG failed to act upon, pay, or contest any of the progress billings submitted by Pro Builders constituted a waiver of its right to question the accuracy and veracity of Pro Builders’ computation. This underscores the importance of adhering to contractual timelines and procedures.

    The Court, citing F.F. Cruz & Co., Inc. v. HR Construction Corp., reiterated the principle that an owner is barred from contesting the contractor’s valuation when it waives its right to demand the joint measurement requirement. Because TG failed to act on the progress billings within the time allowed under the Agreement, it effectively waived its right to contest the computations in the billings.

    The Supreme Court also affirmed the CIAC’s finding that both parties had failed to comply with their obligations under the Agreement. TG had failed to pay the down payment upon signing, as provided in the Agreement, and Pro Builders received the down payment only later. Pro Builders, in turn, had failed to provide sufficient manpower and equipment, causing further delay to the project. This mutual breach of obligations was a key factor in the CIAC’s original decision, and the Supreme Court upheld this aspect of the ruling.

    Consequently, the Supreme Court denied TG’s claim for cost to complete the project, reiterating that this claim was based on TG’s own failure to comply with its obligations under the Agreement. It follows that when both parties are in breach of their contractual duties, neither can unilaterally claim damages or costs from the other without demonstrating their own compliance with the agreement’s terms.

    In conclusion, the Supreme Court’s decision in this case underscores the principle that parties to construction contracts must adhere to the agreed-upon procedures for evaluating and paying for completed works. Failure to do so, especially when it involves neglecting to act upon progress billings within the specified timeframe, can result in a waiver of the right to dispute the contractor’s valuation. The ruling promotes predictability and fairness in construction disputes by reinforcing the importance of fulfilling contractual obligations.

    FAQs

    What was the central legal issue in this case? The key issue was whether TG Universal Business Ventures waived its right to contest Pro Builders’ valuation of completed works by failing to act on the submitted progress billings.
    What did the Construction Industry Arbitration Commission (CIAC) decide? The CIAC partially ruled in favor of Pro Builders, ordering TG to pay for unpaid accomplishments, but this decision was later modified by the Court of Appeals.
    What was the basis for the Court of Appeals’ decision? The Court of Appeals sided with TG, stating all performance inadequacies came from Pro Builders and that the assessment of work was supported by documents.
    On what grounds did the Supreme Court reverse the Court of Appeals’ decision? The Supreme Court reversed the Court of Appeals’ decision, noting that the progress billings were more accurate as TG failed to evaluate and act on it in the agreed period.
    What is the significance of the progress billings in this case? The progress billings were crucial because TG’s failure to act on them within the agreed timeframe resulted in a waiver of its right to dispute the accuracy of Pro Builders’ valuation.
    What does it mean to “waive” a right in the context of this case? In this context, waiving a right means that TG, by its inaction, effectively gave up its ability to contest or dispute the amounts claimed in the progress billings submitted by Pro Builders.
    How did the mutual breach of contract affect the outcome of the case? The Court held that because both parties had breached their contractual obligations, neither could unilaterally claim damages or costs from the other without demonstrating their own compliance with the agreement’s terms.
    What is the key takeaway for parties entering into construction contracts? The key takeaway is that parties must adhere to the agreed-upon procedures for evaluating and paying for completed works and follow a legal expert’s advice to avoid future problems.

    This case highlights the critical importance of adhering to contractual obligations and following agreed-upon procedures in construction contracts. By emphasizing the significance of progress billings and timely responses, the Supreme Court reinforces the need for fairness and predictability in payment disputes within the construction industry.

    For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.

    Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
    Source: PRO BUILDERS, INC. VS. TG UNIVERSAL BUSINESS VENTURES, INC., G.R. No. 194960, February 03, 2016

  • Lease Agreements and Extrajudicial Rescission: Upholding Lessor’s Rights in Contract Disputes

    In Nissan Car Lease Phils., Inc. v. Lica Management, Inc. and Proton Pilipinas, Inc., the Supreme Court affirmed the validity of extrajudicial rescission of a lease contract due to the lessee’s substantial breaches, specifically the non-payment of rentals and unauthorized subleasing of the property. This ruling underscores that lessors can protect their interests by rescinding contracts even without prior court approval, provided the lessee’s violations are significant. The Court clarified that while judicial review of such rescission is possible, lessors are not obligated to passively endure accumulating damages while awaiting a court judgment, ensuring a more equitable balance of rights and responsibilities in lease agreements. This decision provides legal clarity, emphasizing the importance of adhering to contractual obligations and the remedies available to aggrieved parties in lease disputes.

    Broken Promises: Can a Lessor Terminate a Lease Without Court Approval?

    This case originated from a lease agreement between Lica Management, Inc. (LMI) and Nissan Car Lease Philippines, Inc. (NCLPI) for a property in Makati City. NCLPI failed to pay the agreed-upon monthly rent, amassing a substantial debt. Furthermore, without LMI’s consent, NCLPI subleased the property to Proton Pilipinas, Inc. These actions prompted LMI to terminate the lease contract and file a suit to recover the unpaid rentals and damages. NCLPI, in turn, claimed the termination was unlawful and sought damages from both LMI and Proton, alleging a conspiracy to oust them from the property.

    The central legal question revolved around whether LMI could validly rescind the lease contract extrajudicially, given the absence of an express provision in the contract allowing for such action. The trial court ruled in favor of LMI, ordering NCLPI to pay the unpaid rentals, exemplary damages, and attorney’s fees. The Court of Appeals (CA) affirmed this decision with slight modifications. Unsatisfied, NCLPI elevated the case to the Supreme Court, arguing that extrajudicial rescission was improper and that the circumstances did not warrant the dismissal of their claims.

    The Supreme Court began by addressing LMI’s challenge to the validity of NCLPI’s petition, which was based on the argument that the person who signed the petition lacked proper authorization. The Court, however, clarified that the President of a corporation can sign the verification and certification against forum shopping without needing a board resolution. Thus, the petition was deemed valid, and the Court proceeded to address the substantive issues.

    In analyzing the validity of the extrajudicial rescission, the Court emphasized that NCLPI had committed substantial breaches of its Contract of Lease with LMI. NCLPI failed to pay the agreed-upon monthly rental payments and, without LMI’s prior written consent, subleased the property to Proton. The Court cited paragraphs 4 and 5 of the Contract of Lease, which explicitly prohibit subleasing and introducing improvements without the lessor’s consent. NCLPI argued that LMI’s termination of the lease was defective because the demand letter provided only five days to comply, whereas Section 2 of Rule 70 of the Rules of Court requires fifteen days.

    The Supreme Court clarified that NCLPI’s reliance on Rule 70 was misplaced, as that rule applies to actions for forcible entry and unlawful detainer, not to actions for recovery of a sum of money. The Court then addressed NCLPI’s argument that LMI could not unilaterally and extrajudicially rescind the contract without an express provision allowing it. The Court acknowledged previous rulings stating that extrajudicial rescission requires an explicit contractual stipulation, however, the Supreme Court clarified that the remedy of rescission is always available to the injured party under Article 1191 of the Civil Code, regardless of whether the contract expressly stipulates it.

    Art. 1191. The power to rescind obligations is implied in reciprocal ones, in case one of the obligors should not comply with what is incumbent upon him. The injured party may choose between the fulfillment and the rescission of the obligation, with the payment of damages in either case. He may also seek rescission, even after he has chosen fulfillment, if the latter should become impossible.

    The Court further explained that an aggrieved party is not obligated to passively watch damages accumulate while waiting for a court judgment. The act of treating a contract as canceled is provisional and subject to court review. If the court deems the rescission unwarranted, the rescinding party will be liable for damages, but if the rescission is justified, it will be affirmed, and the prejudiced party will receive indemnity.

    The only effect of an express contractual stipulation allowing extrajudicial rescission is that the defaulting party bears the burden of initiating a lawsuit. In this context, the Court concluded that LMI’s extrajudicial rescission was justified, given NCLPI’s non-payment of rentals and unauthorized sublease. Thus, NCLPI was required to pay all rental arrearages. Furthermore, the court addressed the issue of the security deposit, ruling that LMI must return the balance to NCLPI with interest, as per Paragraph 3 of the Contract of Lease.

    The Supreme Court also touched on the issue of improvements made to the property. NCLPI had requested the return of all installed equipment and improvements. The Court pointed out that NCLPI was only entitled to the return of improvements that could be removed without damaging the leased premises. Due to a pending case regarding the ownership of improvements, the Court refrained from ruling on the matter.

    In conclusion, the Supreme Court denied NCLPI’s petition, upholding the CA’s decision with modifications. NCLPI was ordered to pay LMI and Proton exemplary damages and attorney’s fees. NCLPI was also directed to pay the unpaid rentals with interest, while LMI was instructed to return the security deposit with interest. The ruling reinforces the principle that a lessor can extrajudicially rescind a lease contract when the lessee commits substantial breaches, provided that this action is subject to judicial review.

    FAQs

    What was the key issue in this case? The key issue was whether LMI could validly rescind the lease contract extrajudicially due to NCLPI’s failure to pay rent and unauthorized subleasing, despite the contract not explicitly allowing extrajudicial rescission.
    Can a lessor terminate a lease agreement without going to court? Yes, a lessor can terminate a lease agreement without prior court approval if the lessee breaches the contract, such as by failing to pay rent or subleasing without permission, as long as this action is subject to judicial review.
    What happens if the lessee doesn’t pay rent? If the lessee fails to pay rent, the lessor has the right to rescind the lease agreement and demand payment for the unpaid rentals, as well as seek damages for the breach of contract.
    What happens if the lessee subleases the property without permission? If the lessee subleases the property without the lessor’s consent, it constitutes a breach of the lease agreement, giving the lessor the right to terminate the contract.
    Is a lessor required to give a 15-day notice before terminating a lease for non-payment? The 15-day notice requirement under Rule 70 of the Rules of Court applies to actions for forcible entry and unlawful detainer, not to actions for recovery of a sum of money.
    What is the effect of a clause allowing extrajudicial rescission in a lease contract? A clause allowing extrajudicial rescission in a lease contract merely shifts the burden to the defaulting party to initiate a lawsuit, rather than the rescinding party.
    What happens to the security deposit when a lease is terminated? Upon termination of the lease, the lessor must return the balance of the security deposit to the lessee, after deducting any amounts owed for unpaid utilities or damages, with applicable interest.
    Can a lessee claim compensation for improvements made to the property after lease termination? The lessee is only entitled to compensation for improvements that can be removed without causing damage to the property; otherwise, the improvements become the lessor’s property without any obligation to refund the lessee.

    This case provides a clear framework for understanding the rights and obligations of lessors and lessees in the Philippines. The Supreme Court’s decision underscores the importance of adhering to contractual terms and provides remedies for aggrieved parties in lease disputes. By upholding the validity of extrajudicial rescission, the Court ensures that lessors are not left without recourse when lessees breach their contractual obligations. For parties entering into lease agreements, it is crucial to understand these principles and to seek legal counsel to ensure their rights are protected.

    For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.

    Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
    Source: Nissan Car Lease Phils., Inc. v. Lica Management, Inc., G.R. No. 176986, January 13, 2016